Skip to content
Glossary · FEED

What is Front-End Engineering Design (FEED)?

Front-End Engineering Design (FEED), also called Front-End Loading (FEL) or Pre-FEED in some organizations, is the engineering phase that follows conceptual design and precedes full detailed engineering. It produces the engineering package on which the final investment decision for a capital project is made, and it establishes the baseline cost, schedule, and technical scope that the subsequent EPC contract will be built on.
Last reviewed:

Where FEED sits in the project lifecycle

A typical major capital project progresses through:

  • Concept / FEL-1 — high-level feasibility, order-of-magnitude cost estimate (typically ±50 percent)
  • Pre-FEED / FEL-2 — refined process selection, preliminary cost estimate (typically ±30 percent)
  • FEED / FEL-3 — defined engineering package, bid-quality cost estimate (typically ±10 to 15 percent)
  • Detailed engineering — full design package, construction documents
  • Procurement and construction
  • Commissioning and startup

The FEED phase is the bridge between a concept the business has decided to pursue and a project that can be executed by an EPC contractor. It is also the phase where most of the engineering decisions that determine project cost and operability are locked in.

FEED deliverables

A typical FEED package includes:

  • Process Flow Diagrams (PFDs) and heat and material balances
  • Piping and Instrumentation Diagrams (P&IDs) — typically at approximately 80 percent completeness
  • Equipment data sheets for major equipment
  • Plot plan and equipment layout
  • Preliminary piping and electrical specifications
  • Initial control system architecture
  • Hazard identification study (HAZID) and preliminary HAZOP
  • Cost estimate (typically ±10 to 15 percent accuracy)
  • Preliminary project schedule
  • Constructability review

Duration and cost

FEED duration depends on project complexity. A major grassroots refinery or petrochemical facility might require a twelve-to-eighteen-month FEED with dozens of engineers across multiple disciplines. A unit-scale project might run six to nine months with a smaller team.

FEED cost typically runs 2 to 5 percent of total installed project cost — substantial in absolute terms but leveraged against the project decisions it enables. A well-executed FEED reduces execution cost risk; a poorly executed FEED is where most megaproject cost overruns are seeded.

The role of P&IDs in FEED

FEED P&IDs are not the same as operations-ready P&IDs. At the end of FEED, the drawings are typically at approximately 80 percent completeness — the major equipment, lines, and control strategy are defined, but the full instrumentation detail, relief system design, and tie-in details are finalized during detailed engineering.

FEED-stage P&IDs are used for:

  • Preliminary HAZOP analysis
  • MTO for bid-quality cost estimation
  • Plot plan and piping studies
  • Equipment sizing and specification
  • Control philosophy development

The transition from FEED to detailed engineering is a drawing-intensive handover. Engineering firms and EPC contractors commonly inherit FEED drawings from a different contractor than the one executing detailed engineering — creating the same drawing interpretation challenge that operators face on brownfield revamps.

Your drawings, your data

Start with ten of your own drawings.

Definitions are context. The fastest way to see what Armeta does for the workflow this term sits inside is to run it on your actual P&IDs.